Holiday Park Sewage Treatment Plant Sump Pump and Piping Installation at Control Building

Plum Borough Municipal Authority
Allegheny County, PA

NIRA Project No. 35-196-96

*Both Contracts Awarded June 16, 2021

Contractor Contact Person Bid Amount
Plum Borough Municipal Authority
4555 New Texas Road
Pittsburgh, PA  15239
 J. Howard Theis  N/A
ELECTRICAL
PFB Electric, LLC
111 Mt. Vernon Road
Grindstone, PA  15442
David Buberniak $30,080.00
SE Construction Group, LLC
3015 Pickering Run Road
Marion Center, PA  15759
Bri Fleming $44,993.00
Frankl Electric, Inc.
134 Singer Avenue
McKees Rocks, PA  15136
Bryan Lyscik $32,575.00
Genesis Construction Group
P.O. Box 1045
Mount Pleasant, PA  15666-1045
Thomas G. Vivian $26,562.00*
Schultheis Electric/T.S.B., Inc.
P.O. Box 798
Latrobe, PA  15650-0798
Tim Schultheis $31,750.00
MECHANICAL
JP Environmental, LLC
2693 Lower Road
Shamokin, PA  17872
Jeff Pickens $107,000.00
SE Construction Group, LLC
3015 Pickering Run Road
Marion Center, PA  15759
Bri Fleming N/A
Lone Pine Construction, Inc.
83 Lusk Road
Bentleyville, PA  15314
Marty Weir N/A
Kukurin Contracting, Inc.
1169 Rt. 286
Export, PA  15632
Sandy Pulsifer $144,441.00
Clair Plumbing, LLC
4224 Stanley Street
Pittsburgh, PA  15207
Steven Clair $96,725.00*
Port Vue Plumbing, Inc.
3716 Liberty Way
McKeesport, PA  15133
Jerry Brewer $129,000.00
First American Industries, Inc.
617 California Avenue
Pittsburgh, PA  15202
Bethany Vargo N/A
S.E.T., Inc.
235 E. Water Street
Lowellville, OH  44436
Moussa Bittar $128,819.00